  • #151 by VirginiaHog on 02 May 2017
  • Steel time. Bout to get moving.
  • #152 by GoHogzzGo on 02 May 2017
  • Steel time. Bout to get moving.

    Woohoo! Looking good.
  • #153 by Boog41 on 02 May 2017
  • I know it is only a temporary view, but it strikes me as odd seeing the south closed in with the north open.......after the exact opposite for all those years.
  • #154 by jkstock04 on 02 May 2017
  • The new scoreboard looks absolutely gigantic to the naked eye, I can tell you that.
  • #155 by VirginiaHog on 02 May 2017
  • 5 steel beams already up. It goes so fast it just messes you up.  :razorback:
  • #156 by FraggleHog on 02 May 2017
  • The new scoreboard looks absolutely gigantic to the naked eye, I can tell you that.

    Well, it's not really new (other than it's location in the stadium)... Its the exact scoreboard that was in the NEZ in previous seasons. Maybe it just seems bigger because its higher up and we've never seen anything in that space before.
  • #157 by FraggleHog on 02 May 2017
  • Steel time. Bout to get moving.

    I bet it's "American Steel"  ;)
  • #158 by Jackrabbit Hog on 02 May 2017
  • 5 steel beams already up. It goes so fast it just messes you up.  :razorback:

    You reckon when they finish the DWRRS job, we can get that crew on I-40 between Memphis and Little Rock?
  • #159 by ricepig on 02 May 2017
  • You reckon when they finish the DWRRS job, we can get that crew on I-40 between Memphis and Little Rock?

    What would you use for an excuse to drive by Craig's?
  • #160 by Jackrabbit Hog on 02 May 2017
  • What would you use for an excuse to drive by Craig's?

    Sssshhhhh!!!!  Craig's is where Deltaboy and I meet once a month to discuss Hogville and our posting strategy. 
  • #161 by ricepig on 02 May 2017
  • Sssshhhhh!!!!  Craig's is where Deltaboy and I meet once a month to discuss Hogville and our posting strategy. 

    There's a strategy to this.......
  • #162 by LZH on 02 May 2017
  • You reckon when they finish the DWRRS job, we can get that crew on I-40 between Memphis and Little Rock?

    Hasn't there been one there since around 1975?
  • #163 by Sivad on 02 May 2017
  • With two videoboards, now when they light it up red at night it should really be awesome.
  • #164 by Inhogswetrust on 02 May 2017
  • You reckon when they finish the DWRRS job, we can get that crew on I-40 between Memphis and Little Rock?

    That stretch of I-40 will NEVER be finished.
  • #165 by jkstock04 on 02 May 2017
  • Well, it's not really new (other than it's location in the stadium)... Its the exact scoreboard that was in the NEZ in previous seasons. Maybe it just seems bigger because its higher up and we've never seen anything in that space before.
    Wow, I never would've guessed that. Maybe it's just the positioning there on the south end but I thought it looked 2 or 3 times as big.
  • #166 by Iwastherein1969 on 03 May 2017
  • You reckon when they finish the DWRRS job, we can get that crew on I-40 between Memphis and Little Rock?
    that will never be finished, it's a sinister plan by Damian Echols who is calling upon Lillith to forever keep West Memphis a haven of white trash and just trash in general
  • #167 by Boss Hog in the Arkansas on 03 May 2017
  • that will never be finished, it's a sinister plan by Damian Echols who is calling upon Lillith to forever keep West Memphis a haven of white trash and just trash in general
    That may be the funniest thing I've seen on here this offseason
  • #168 by Boss Hog in the Arkansas on 03 May 2017
  • This is just insane.
  • #169 by RazorBassin on 03 May 2017
  • Wow, really coming along.  I'm not a Civil Engineer, but how will all of this rain affect the building/longevity of this project.  I just don't want them to get it built, and then we have a settling problem.  I'm sure with the amount of money they are making on this project, that the construction team will ensure the highest quality of work.  But, being around a lot of government contracting and seeing the cheapest bidder more often than not do the crappiest job, I was just curious.
  • #170 by Pig in the Pokey on 03 May 2017
  • I bet it's "American Steel"  ;)
    yeah, not much of a chance of that...
  • #171 by Pig in the Pokey on 03 May 2017
  • With two videoboards, now when they light it up red at night it should really be awesome.
    gonna look like the inside of my beast gaming pc in there! RGB
  • #172 by Pig in the Pokey on 03 May 2017
  • that will never be finished, it's a sinister plan by Damian Echols who is calling upon Lillith to forever keep West Memphis a haven of white trash and just trash in general
    bro, those dudes are innocent;

    but since you said lillith, ill give you a pass lol
  • #173 by Boss Hog in the Arkansas on 03 May 2017
  • Wow, really coming along.  I'm not a Civil Engineer, but how will all of this rain affect the building/longevity of this project.  I just don't want them to get it built, and then we have a settling problem.  I'm sure with the amount of money they are making on this project, that the construction team will ensure the highest quality of work.  But, being around a lot of government contracting and seeing the cheapest bidder more often than not do the crappiest job, I was just curious.
    Sorry sir that's above my pay grade. I just buy tickets and show up.... like a good little razorback kool aid drinker  :D
  • #174 by ricepig on 03 May 2017
  • Wow, really coming along.  I'm not a Civil Engineer, but how will all of this rain affect the building/longevity of this project.  I just don't want them to get it built, and then we have a settling problem.  I'm sure with the amount of money they are making on this project, that the construction team will ensure the highest quality of work.  But, being around a lot of government contracting and seeing the cheapest bidder more often than not do the crappiest job, I was just curious.

    This is a cost+ job, they aren't skimping on the details. Outside of last weekend, there hasn't been an inordinate amount of rain in Fayetteville this winter, probably below average.

    https://www.drought.gov/drought/arkansas
  • #175 by Boss Hog in the Arkansas on 03 May 2017
  • This is a cost+ job, they aren't skimping on the details. Outside of last weekend, there hasn't been an inordinate amount of rain in Fayetteville this winter, probably below average.

    https://www.drought.gov/drought/arkansas
    Its very below average. Jeff long made a comment about it last week saying that they've been able to get ahead of schedule because of it
  • #176 by ricepig on 03 May 2017
  • Its very below average. Jeff long made a comment about it last week saying that they've been able to get ahead of schedule because of it

    Crane #2 has arrived, looks like they will start putting it together.
  • #177 by Jackrabbit Hog on 03 May 2017
  • Its very below average. Jeff long made a comment about it last week saying that they've been able to get ahead of schedule because of it

    So the rain is tracking right along with the football program.  Appropriate.




    I keed.  I keed.
  • #178 by razorbackfan4life on 03 May 2017
  • Progress is good.  Luckily they can work in the rain now that the dirt work seems to be done. 
  • #179 by LZH on 03 May 2017
  • Wow, really coming along.  I'm not a Civil Engineer, but how will all of this rain affect the building/longevity of this project.  I just don't want them to get it built, and then we have a settling problem.  I'm sure with the amount of money they are making on this project, that the construction team will ensure the highest quality of work.  But, being around a lot of government contracting and seeing the cheapest bidder more often than not do the crappiest job, I was just curious.

    The soil/foundation was prepped before construction began (sand). And they won't work on much unless its dry enough.
  • #180 by Boss Hog in the Arkansas on 04 May 2017
  • The speed these guys are working is just incredible
  • #181 by FraggleHog on 04 May 2017
  • The speed these guys are working is just incredible

    Now that the foundation work is done... The frame should go up pretty quickly!
  • #182 by Rock City Razorback on 04 May 2017
  • The speed these guys are working is just incredible

    I wonder if it was a contract similar to the Broadway Bridge in that if they get it completed by a certain date, they receive more compensation.
  • #183 by Boss Hog in the Arkansas on 04 May 2017
  • I wonder if it was a contract similar to the Broadway Bridge in that if they get it completed by a certain date, they receive more compensation.
    I started to make a joke about that earlier lol
  • #184 by ricepig on 04 May 2017
  • Now that the foundation work is done... The frame should go up pretty quickly!

    Shoot, we're already out of steel......
  • #185 by Boss Hog in the Arkansas on 05 May 2017
  • Shoot, we're already out of steel......
    I thought you were making a joke until I scrolled around the NEZ. No, we are seriously out of steel lol
  • #186 by Boss Hog in the Arkansas on 05 May 2017
  • Plans have changed, suites will not be added to the NEZ. Instead, boosters have decided to take the "game day experience" to the next level by building a small theme park. The 1st addition will be a large yellow roller coaster that can be taken from the west side of the stadium to the east side. *satire*  :D
  • #187 by OneTuskOverTheLine™ on 05 May 2017
  • You reckon when they finish the DWRRS job, we can get that crew on I-40 between Memphis and Little Rock?

     There's been perpetual construction somewhere on that stretch since 1991...
  • #188 by ricepig on 05 May 2017
  • There's been perpetual construction somewhere on that stretch since 1991...

    Just be glad they are working on it, it could become a gravel road again, haha.
  • #189 by Hawgar The Horrible on 05 May 2017
  • Just be glad they are working on it, it could become a gravel road again, haha.

    Between construction and truckers driving 50 mph side-by-side for 20 mile stretches at a time (I swear they do that on purpose), I now take 64 from Marion to Conway without hesitation.
  • #190 by Hawgar The Horrible on 05 May 2017
  • More iron now on site.
  • #191 by FraggleHog on 05 May 2017
  • More iron now on site.

    Whew! I was worried there for a minute... /s
  • #192 by Boss Hog in the Arkansas on 08 May 2017
  • Looks like they had a very productive weekend
  • #193 by Stephen Greene on 08 May 2017
  • .
  • #194 by Stephen Greene on 08 May 2017
  • .
  • #195 by sowmonella on 08 May 2017
  • #196 by Jackrabbit Hog on 08 May 2017
  • Hey...move your fingers!!

    That's the sun setting. 
  • #197 by GoHogzzGo on 08 May 2017
  • .

    That is awesome perspective man thanks for posting! Keep 'em coming if you get the chance.

    Really shows how big/deep that hole is. Curious based on the new metal where the red bleachers will come up to.
  • #198 by Boss Hog in the Arkansas on 09 May 2017
  • Coming along nicely
  • #199 by FANONTHEHILL on 09 May 2017
  • This was taken May 9th at 1:00pm from Stadium Drive.  Second level steel on west side coming along nicely.
  • #200 by ricepig on 09 May 2017